Work has continued along Mead Way during lockdown, which has been challenging at times for all involved and we would like to thank you for your patience while these works are ongoing.
Kerbside gullies have been installed in the south section of Mead Way. The old approach traffic islands have been removed as part of the site clearance and the new islands have been built. Approximately 30m of traffic signal ducting and associated chambers have also been installed, which you can see in the photo below.
The utilities that were previously restricted from attending sites nationally by COVID-19 are now beginning to carry out their diversion work.
The street lighting columns have now also been installed.
The stretch of road between the Meads and Westmead roundabouts still remains under a full 24/7 closure.
|